DLI 9 : Water sector intergovernmental Planning, Coordination and Monitoring reforms implemented

Disbursement criteria

9.1 Approval and implementation of a Water Sector Performance-based Financing Mechanism (Yes/No)

$2,000,000 upon cabinet approval

Disbursements against this sub-DLI will be triggered upon approval by the Cabinet of a National Water Sector Performance-based Financing Mechanism (as defined in Section 11 in the POM).

Payment may only be made once under DLI 9.1 during the Program.

9.2 Implementation of the Water Sector Inter-Governmental Coordination Framework including annual joint M&E reporting by both levels of government

US$500,000 annually upon launch of the Water sector M&E report and Joint sector coordination report

Disbursement against this sub-DLI will be triggered for each year during the Program that the joint coordination framework secretariat publishes:

  1. an Annual Water Sector Report aligned to the SDGs according to the template defined in Annex 9. The report will include the progress towards implementation of NAWASIP, and annual intergovernmental coordination activities, and will be jointly published by the national government (MoWSI) and the CoG.

Payment will be made each year during the Program period that DLI 9.2 is verified as achieved.

Verification Protocol – IVA Procedure

Before You Submit

Make sure you have carefully reviewed all eligibility criteria and have all required documentation ready. If you meet all the criteria outlined above, click the submit button to proceed to the submission portal.

Submit Results